Syrian International Academy for Diving & Paragliding

An integrated marine, tourism and training investment on the Latakia coast.

+0
direct jobs
$0M
initial capital
Summer 2027
Opening
0
divisions

Timeline

Fifteen months to opening, Summer 2027

15/ 15 mo
  1. 1

    Phase 1

    Plans & engineering design

    3 months

  2. 2

    Phase 2

    Site preparation & preliminary works

    2 months

  3. 3

    Phase 3

    Construction

    6 months

  4. 4

    Phase 4

    Finishing, fit-out & trial operation

    4 months

Summer 2027

Budget

Initial capital allocation

Budget allocation

USD 1,100,000

Location

Latakia Coastal Sports City

A direct seafront location with easy access, high touristic & investment value, excellent expansion potential, and proximity to the city's tourism activity.

35.5138°N, 35.7793°E